Workflow Overview Report - What is the logic behind 'Expected Completion Date'?

  • June 26, 2024
  • 1 reply
  • 20 views

Forum|alt.badge.img+1

I’m running a workflow overview report and wanted to know the logic behind the column 'Expected Completion Date'. How is this field calculated?

Best answer by Pawan Gangwani

Hello @wilmyers 

I hope you doing great. I was also in search of the same but could no found anything on DS support.
but down the line, I do some tests and found that this “Expected Completion Date” is getting calculating based on your previous workflow completion time around. It tracks the workflow like how many days takes to complete the Workflow and according to that it gives is “Expected Completion Date”.

I hope this helps. Thanks!

View Original
Is this content helpful?

1 reply

Pawan Gangwani
Rising Star
Forum|alt.badge.img+13

Hello @wilmyers 

I hope you doing great. I was also in search of the same but could no found anything on DS support.
but down the line, I do some tests and found that this “Expected Completion Date” is getting calculating based on your previous workflow completion time around. It tracks the workflow like how many days takes to complete the Workflow and according to that it gives is “Expected Completion Date”.